StreetsLA is scheduled to resurface Los Feliz Blvd from Riverside Drive to Vermont Avenue over the course of three weekends. Here is the schedule:
- CANCELLED – Weekend of Saturday October 16, 2021 and Sunday October 17, 2021 Commonwealth and Griffith Park Blvd
- Weekend of Saturday October 23, 2021 and Sunday October 24, 2021 Commonwealth and Griffith Park Blvd
- Weekend of Saturday October 30, 2021 and Sunday October 31, 2021 Griffith Park Blvd and Riverside Drive
The first phase will require the preparation of the existing roadway by cold milling the street. The final phase will require the paving of the existing roadway and resurfacing the street. If the project length is delayed, you will be notified of the reason for the delay and of the revised completion date.
While the project is in progress, “Temporary No Parking Signs” will be posted on the street. The signs will be posted at least 24 hours before the actual work begins to provide notice to residents and business owners. Please have all vehicles removed from the street to protect them from damage by construction debris and to prevent interference with the planned work. When work is not in progress between the preparation and resurfacing phases the signs will be reversed to allow for vehicular parking.
Vehicles will have access during the cold milling of the project. However, it is requested that driving be limited within the project area to avoid possible damage to your vehicle. The only time that access will be restricted within the project area is when the street is coated with liquid asphalt, prior to the resurfacing of the street.
If you have any questions or concerns please feel free to contact the StreetsLA Superintendent at 213-923-5296.